Define the main and auxiliary hook loads, ladle movement envelope and heat exposure for a meltshop crane enquiry.

Equipment reference1601746711566Configured for your project
Technical offer defines final specification
EQUIPMENT-FAMILY REFERENCERed heavy bridge crane inside a high industrial bay.

Red overhead bridge crane with a suspended hook block in an industrial bay. This corresponding archive photograph illustrates the arrangement; it does not establish the selected 225/65 t ratings or protection functions.

Selection at a glance
225 t main / 65 t auxiliary

Separate enquiry references; selected ratings to agree

Hook duties
Separate main/auxiliary load cases
Clearance
Vessel, rigging and full motion envelope
Duty and heat
Process cycle and actual exposure
Site interfaces
Runway, power and supply responsibilities
Prepare my enquiry

Start with your known requirements. Our team can clarify the remaining interfaces.

01

Specification without the guesswork.

Separate the listed product information from the dimensions and responsibilities that need your project input.

Product data

225/65 t Ladle Crane: Meltshop Duty and Clearance listed specifications
Separate hook references225 t main / 65 t auxiliary enquiry references; do not add them. Agree each hook rating and every permitted combined-use load case.
Suspended-load scheduleVessel tare, maximum contents, lifting beam and attachments; define the applicable rated-load basis and hook loads at each process stage
Process and tipping envelopePickup, transfer, pouring, standby and set-down positions; vessel geometry, rigging, tilt path and restricted areas
Span and runway interfaceSurveyed rail-centre dimensions, rail section and top level, building clearances, selected wheel loads and support review
Useful hook positionsRequired upper/lower positions for each hook and the clearance needed with the ladle and rigging in place
Archived lift alternativesSupplier family listing gives 6, 10, 20, 32 and 55 m alternatives; the selected drawing defines usable hook movement
Duty and classificationLoad spectrum, cycles, starts, shifts and process delays; specify crane and mechanism classifications under the agreed standard
Thermal exposureAmbient conditions, radiant heat, exposure duration and equipment location; agree shielding and component limits for the route
Motors and electrical protectionSelected ingress protection, insulation system, cooling and electrical ratings; these do not alone establish whole-crane thermal suitability
Controls and protective functionsOperator position and view, selected motions, limits, braking and interlocks; document functions and acceptance requirements
Site electrical supplyActual voltage, frequency, phase, power-feed route and isolation requirements; specify matching equipment in the offer
Supply and acceptance scopeEquipment, runway/power work, unloading/erection, process testing, commissioning, documents, training and contractual service responsibilities

Listed information supports initial selection. Final dimensions, loads, speeds and components are defined in the project technical offer.

Site interfaces

Ladle route and hook loads

Provide vessel/rigging geometry and a load schedule for pickup, transfer, pouring and set-down. Identify main/auxiliary tasks and proposed coordinated motions.

Runway and working clearance

Provide surveyed rail centres, rail section/top level, upper/lower hook positions, approaches and building/support drawings. Obtain selected wheel loads for structural review.

Duty, heat and services

State cycles, starts, shifts, heat exposure at equipment locations, operator view and local power. Agree the operating limits and site responsibilities.

Supply scope

Supply responsibilities to confirm
Work packageAgree in the quotation
Crane and protective functionsSelected bridge/trolleys, separate hook mechanisms, controls, braking/limits/interlocks and documented operating conditions.
Runway and electrical interfacesAllocated supporting structure, rails, moving power feed, isolation, local wiring and structural review.
Delivery and erectionNamed delivery term, package/handling information, unloading, access equipment, erection and commissioning responsibilities.
Acceptance and handoverAgreed inspection/testing, load-case records, matching drawings/manuals, training, parts and contractual service terms.

This is a scope-planning checklist. Inclusion and responsibility depend on the agreed contract.

02

Check the job before choosing the equipment.

Review the complete process load case, vessel movement and thermal exposure against the selected arrangement.

Use the Site interfaces tab above to check the layout and operating conditions. Record your requirements in the project brief alongside this page.

03

Detailed equipment information.

Review the product configuration and purchasing requirements for this equipment.

Equipment and application overview

A meltshop crane enquiry needs a process load case, not just a tonnage label. For this 225/65 t ladle-crane reference, identify the main and auxiliary hook tasks separately, then map the full vessel and rigging envelope through pickup, transfer, pouring and set-down. Compare operating duty, heat exposure and runway inputs on the same project drawing. The supplier listing provides a starting reference; the selected ratings, permitted motions and protection functions belong in the technical offer.

Equipment family
Foundry / ladle overhead crane
Hook references
225 t main and 65 t auxiliary; separate duties and approved load cases
Comparison basis
Process load, vessel clearance, thermal exposure and operating cycle
Required documents
Arrangement drawing, process load schedule, runway inputs and itemized scope

LOAD · ROUTE · EXPOSURE

Review the casting cycle before comparing offers

Use the same operating sequence and layout when evaluating alternative crane configurations.

Build a stage-by-stage load schedule

Record vessel tare, maximum contents, beam and attachment masses. Identify what each hook supports during pickup, transfer and pouring, and ask for permitted combinations rather than assuming two independent maximum loads can act together.

Check the moving vessel envelope

Mark furnace and receiving-station geometry, hook levels, approaches, columns, maintenance access and restricted areas. Check clearance through the intended motion, including vessel tilt and rigging, with the selected drawing.

Describe duty and heat separately

Provide load cycles, travel distances, starts, shifts and holding periods. State ambient and radiant exposure at the equipment locations; agree the applicable classifications, shielding, cooling and operating limits in the offer.

CORRESPONDING ARCHIVE PHOTOGRAPHS

Read the arrangement without assuming the selected rating

These three photographs are in this product archive. They show equipment views; the project drawings define capacity, process clearances and protective functions.

Red heavy bridge crane inside a high industrial bay.01 / EQUIPMENT-FAMILY REFERENCE

Bridge and suspended hook block

Red overhead bridge crane with a suspended hook block in an industrial bay. This corresponding archive photograph illustrates the arrangement; it does not establish the selected 225/65 t ratings or protection functions.

Yellow multi-girder bridge viewed from below.02 / EQUIPMENT-FAMILY REFERENCE

Multi-girder underside view

Yellow multi-girder bridge viewed from below. Use the selected arrangement drawing to check girder, trolley and hook clearances; the photograph does not establish the quoted load case.

Red overhead bridge crane inside a steelmaking workshop03 / EQUIPMENT-FAMILY REFERENCE

Crane above a steelmaking work area

Red overhead bridge crane above a steelmaking work area. Treat this as an equipment-family view, then define the actual process route, heat exposure and operating restrictions in the project review.

DEFINE THE SELECTED SYSTEM

Separate the crane package from the meltshop interfaces

Itemize bridge and trolley arrangements, main/auxiliary mechanisms, controls, power feed and the agreed protective functions. Request matching load cases, wheel loads, dimensions and operating limits.

Allocate runway and support work, electrical supply, unloading, erection and access equipment. Agree the inspection and process-test plan, commissioning sequence, records, operator handover and contractual service terms. Historical listing descriptions of brakes, thermal layers or component brands do not define the selected system.

PROCESS LAYOUT AND OPERATING CYCLE

Send the route, load stages and thermal conditions

Include vessel and rigging geometry, pickup/pouring/set-down positions, hook levels, rail-centre dimensions, support drawings and equipment access. Add operating shifts, cycle frequency, exposure locations and the actual site electrical supply.

Discuss your meltshop requirements

Henan Mine Crane Group

Agree a documented basis for quotation and acceptance

Keep equipment references, revision dates and responsibility boundaries consistent across the offer and drawings.

Selected technical offer

Identify separate hook ratings, approved load cases, crane and mechanism duty, speeds, controls, thermal provisions and applicable standards. Resolve differences with the operating sequence before ordering.

Site and installation plan

Review wheel loads and runway interfaces with the responsible structural designer. Allocate power, access, erection, isolation and site preparation in the agreed supply scope.

Acceptance and handover

Agree inspection, functional and applicable load/process testing, required records, matching manuals, training and spare-parts identification. State warranty and service obligations in the contract.

Archived supplier reference

Historical supplier-listing information for context. Request a current quotation for your selected configuration and project scope.

Archived supplier-listing price rangeUS$890,000–900,000per set · MOQ 1 set

Range combines the price tiers shown in the saved listing. Captured 2026-10-12. This is not a current project quotation; capacity, dimensions, options, quantity, delivery and included services affect final price.

Show saved supplier price tiers
  • 1-2 setsUS$900,000 / set
  • ≥3 setsUS$890,000 / set

Archived supplier-listing reference. The saved price is not a current quotation; confirm configuration, quantity, shipping and included scope. View saved source listing ↗

04

One clear package for your buying team.

Bring engineering, purchasing and the installation team into the same scope before the purchase order.

Your layout is more useful than a generic catalogue.

Send the vessel and rigging layout, stage-by-stage main/auxiliary hook loads, operating route, hook levels and runway/support drawings. Add duty, heat exposure, site power and installation responsibilities.

Send a drawing for review
YOU PROVIDE

Project brief

Load or working task, layout, operating cycle, destination and timing.

REVIEW TOGETHER

Technical offer

Selected configuration, interface drawing, component schedule and scope exceptions.

Compare like for like. Ask each bidder to identify the selected equipment, operating duty, interfaces and supply boundaries so differences in the offers are visible.
05

Questions before you request a quotation.

Can 225 t and 65 t be added as one lifting capacity?

No. This listing uses a main/auxiliary hook reference. The selected technical documentation must state each hook rating, allowed combined load cases and permitted movements. Do not infer a 290 t rating or simultaneous maximum loading from the pair.

What must the process-clearance drawing include?

Include the vessel and rigging envelope, hook levels, pickup and pouring positions, full intended tilt path, approaches, nearby structures and restricted areas. Use the selected arrangement and load cases to review clearance throughout the movement.

Does an IP55 motor or insulation class H prove thermal suitability?

No. Motor ingress protection and insulation classification address particular component properties. Whole-system suitability depends on the actual ambient and radiant exposure, duration, location, shielding, cooling and selected component limits. Agree those conditions for the meltshop route.

How should duty classifications and lift alternatives be specified?

Provide the load spectrum, cycles, starts, shifts and process sequence, then agree crane and mechanism classifications under the applicable standard. Do not assume ISO/FEM labels are interchangeable. The archived 6, 10, 20, 32 and 55 m options do not establish the selected useful hook movement.

Is US$890,000–900,000 a current delivered and installed price?

The supplier listing captured 2026-10-12 shows US$900,000 per set for 1–2 sets and US$890,000 for at least 3 sets. These historical tiers are not a current project or delivered quotation. Compare an itemized offer for the selected crane, protection functions, runway interfaces, delivery and site services.

225 t main / 65 t auxiliaryOverhead cranes
Request a quotation

Henan Mine Crane Group

Let’s plan your next lift.

Share your site and lifting requirements. Our team will review a suitable configuration.

Loading the inquiry form…