03 / Site execution
Keep installation scope clear before equipment arrives.
The best crane selection can still be delayed by an unready runway, missing power supply or unclear lifting plan. Put the site interfaces and commissioning responsibilities into the contract.
What the buyer needs to resolve
“Installation included” is too vague to schedule people, tools, utilities and acceptance work across supplier and buyer teams.
Validate the site interface
Confirm runway geometry, rail or support condition, building clearances, foundations where relevant and electrical supply against the approved crane drawing. Identify who surveys and signs off each interface before dispatch.
- Runway, rail, foundation and access drawings
- Voltage, frequency and power-feed location
- Clearances, hook approach and maintenance access
Split the work by party
List who provides erection supervision, labour, mobile cranes, scaffolding, tools, temporary power, permits and local regulatory coordination. Include access windows and lifting restrictions so the installation programme can be priced realistically.
- Supplier and buyer responsibility matrix
- Erection equipment and local labour
- Permits, site safety and work schedule
Define commissioning and acceptance
Agree mechanical and electrical checks, safety-device settings, functional trials and load tests required at site. Specify test loads, instruments, witnesses and acceptance criteria under applicable local rules and the project specification.
- Commissioning sequence and test procedure
- Open-issue and re-test process
- Signed acceptance and start-of-operation criteria
Close out the project properly
Request as-built information, manuals, inspection records and a clear list of residual work. Decide when responsibility transfers to operations and what starts the warranty period; state these dates in the contract.
- Document handover and final drawing revision
- Training and spare-parts handoff
- Warranty start and outstanding-item closure
Before you approve the order
Agree the runway and utilities checklist, a responsibility matrix and a site-acceptance procedure before order placement.
Turn “installation included” into a responsibility matrix
Use a matrix with one named lead for every work package. Record who supplies labour, equipment, materials and sign-off, then add the required output and ready date. The split below is a contract checklist; it does not presume which party has agreed to perform the work.
Swipe across the table to view all columns.
| Work package | Output to assign and approve |
|---|---|
| Site and runway readiness | Survey records, structural acceptance, rail geometry, access route and clearance review against the approved crane drawing. Name the party that closes deviations. |
| Mechanical erection | Approved erection plan, lifting equipment, qualified personnel, tools and work-area control. State whether the supplier provides supervision or performs the installation. |
| Electrical connection | The incoming supply boundary, isolation, earthing, power-feed installation and responsibility for local electrical approval. Identify the connection point on the drawing. |
| Commissioning and site tests | Agreed procedure, test loads, instruments, competent test personnel, required witnesses and signed results. Name who resolves and retests any failed item. |
| Handover | Final manuals and drawings, training records, open-item closure and written authorisation for operational handover under the applicable site requirements. |
Before dispatching an installation team, hold a site-readiness review against this matrix. Confirm that the approved drawings are current, the runway and utilities are ready, the erection route is available and the agreed test resources can be provided. Record exceptions and their effect on mobilisation rather than relying on a general “site ready” message.
Put travel, accommodation, local permits, waiting time, return visits and out-of-scope work into the commercial agreement where relevant. Distinguish factory inspection from site acceptance, and define the warranty start separately in the contract. This keeps the planned start of operation tied to completed checks and handover.
Continue your purchase planning
Review related topics and include the relevant questions in your enquiry.
Discuss the scope with our team.
Tell us your project country and lifting task. Share the drawings and requirements available now; the final technical and commercial scope should be confirmed in the offer.
Request a crane quotation →These checklists are procurement guidance. Equipment, services, tests and warranties are subject to the agreed contract and local requirements.












