Overhead cranes / Engineering selection

20 ton Hoist-Type Double Girder Crane: Clearance and Runway

Plan the 20 ton hoist-type bridge crane around rigging depth, useful hook positions, roof clearance and the selected runway reactions.

Equipment reference1601281586079Configured for your project
Technical offer defines final specification
PRODUCT-FAMILY REFERENCEYellow double-girder bridge crane above red fabrication equipment.

Yellow double-girder crane above red fabrication equipment. Product-family reference photograph; the visible workshop scene does not establish the selected 20 ton configuration or its dimensions.

Selection at a glance
20tonnes

Enquiry load; selected configuration to be agreed

Enquiry load
20 t; complete suspended-load basis
Lifting package
Selected wire-rope hoist trolley on double girders
Clearance review
Hook workpoints, rigging depth and roof limits
Runway review
Selected wheel reactions and support drawings
Prepare my enquiry

Start with your known requirements. Our team can clarify the remaining interfaces.

01

Specification without the guesswork.

Separate the listed product information from the dimensions and responsibilities that need your project input.

Product data

20 ton Hoist-Type Double Girder Crane: Clearance and Runway listed specifications
Enquiry and load basis20 t enquiry; include the lifted workpiece and below-hook slings, lifting beam and attachments in the suspended-load requirement. Do not deduct the integral hook block again; obtain crane/trolley self-weight separately for support design.
Lifting arrangementDouble-girder bridge with the selected electric wire-rope hoist trolley; verify the matched hoist, bridge and duty
Runway geometryArchived span alternatives 10.5–31.5 m; selected rail centres, rail profile, runway length, levels and approaches to be agreed
Hook working envelopeArchived lift alternatives 6, 9, 12 or 18 m; define required upper/lower hook positions, reeving, rigging depth and obstruction clearance
Duty and motion scheduleArchived A4 selection within an intermittent A3–A4 family; confirm load spectrum, lifts/starts, shifts and selected lifting/trolley/bridge speeds
Runway design actionsSelected crane and trolley masses, wheel arrangement and reactions for relevant trolley positions, plus agreed horizontal and dynamic actions
Power and controlsArchived 380 V, 50 Hz, three-phase option; agree site supply, moving feed, isolation, controls and safety functions
Installation and acceptanceAllocate runway assessment, rail work, erection access, power connections, inspection/testing and handover in the offer

Listed information supports initial selection. Final dimensions, loads, speeds and components are defined in the project technical offer.

Site interfaces

Working envelope

Supply pickup/placement positions, rigging dimensions, load geometry, roof/services section and selected hook limits.

Runway and structure

Provide rail centres/profile/levels, runway and support drawings, existing condition and end stops; request selected reactions for structural review.

Cycle, supply and access

State load spectrum, lifts and starts per hour, shifts, travel, speeds, voltage/frequency/phases, environment and erection/maintenance access.

Supply scope

Supply responsibilities to confirm
Work packageAgree in the quotation
Crane packageSelected double-girder bridge, hoist trolley, motion drives, controls and agreed safety functions identified.
Runway and power interfacesStructural assessment, rail supply/alignment, stops, moving feed, isolation and site connections allocated.
InstallationTransport, unloading, lifting access, erection, alignment and commissioning responsibilities listed.
Acceptance and handoverApplicable inspection/testing, records, coordinated drawings, manuals, training, spares and warranty terms agreed.

This is a scope-planning checklist. Inclusion and responsibility depend on the agreed contract.

02

Check the job before choosing the equipment.

Check whether the chosen hoist-type arrangement can reach the workpoints with the actual load and rigging. Review the operating cycle and selected support actions before agreeing the technical offer.

Use the Site interfaces tab above to check the layout and operating conditions. Record your requirements in the project brief alongside this page.

03

Detailed equipment information.

Review the product configuration and purchasing requirements for this equipment.

Equipment and application overview

A 20 ton hoist-type double-girder crane needs one coordinated envelope for the hoist trolley, hook, lifting attachments and load. Start with the pickup and set-down positions, then compare the selected headroom, hook approaches and runway reactions. Building height and nominal capacity alone do not establish that the crane will fit or that an existing runway can support it.

Equipment enquiry
20 ton hoist-type double-girder bridge crane
Clearance decision
Selected trolley/headroom and hook approaches checked against workpoints and obstructions
Support decision
Selected wheel reactions reviewed against runway, columns and supporting structure

CHECK THE OPERATING ENVELOPE

Review clearance at the workpoints

Use a plan and section with a common datum. The crane must reach the required load positions throughout the route, including the approach to machines, storage positions and maintenance areas.

Rigging depth and useful lift

Record lifting-beam or spreader depth, sling geometry, lifting points and load height. A deeper below-hook arrangement can reduce the usable load position even when the hook travel is unchanged. Ask for the selected upper and lower hook positions and reeving arrangement.

Side and end approaches

Mark the required pickup and set-down points relative to the runway rails and end stops. Compare the selected hook approaches with these points; rail-centre span and bridge travel are not the same dimensions as the usable hook coverage.

Roof and service access

Include rafters, lights, ducts, cables and adjacent equipment in the clearance section. Allow the access and removal route needed for the selected hoist, trolley and electrical equipment. Agree required clearances and tolerances in the project drawing rather than assuming a universal allowance.

READ THE REFERENCE PHOTOGRAPHS

Workshop views and their limits

These views come from this product listing’s own saved library. They illustrate equipment-family features and do not establish the selected 20 ton configuration, dimensions, duty or support loads.

Yellow double-girder bridge crane above red fabrication equipment.01 / FAMILY REFERENCE

Bridge crane in the fabrication workshop

Yellow double-girder crane above red fabrication equipment. Product-family reference photograph; the visible workshop scene does not establish the selected 20 ton configuration or its dimensions.

Yellow double-girder crane marked 400/100t with a hook and suspended rigging inside a workshop02 / FAMILY REFERENCE

Different rating shown: 400/100t

Crane visibly marked 400/100t, with a suspended hook and rigging. This product-family photograph is not the 20 ton crane configuration; do not use the pictured markings, load or proportions for this enquiry.

Underside of yellow overhead crane girders with suspension hardware and hook blocks beneath a workshop roof03 / FAMILY REFERENCE

Suspension hardware and hook blocks

Yellow overhead girders, suspension hardware and hook blocks viewed from below. Product-family reference photograph; selected reeving, hook count, approaches and headroom require the order drawing.

REVIEW THE RUNWAY ACTIONS

Obtain reactions for the selected crane

Ask for the wheel arrangement, wheelbase, crane and trolley masses, and wheel reactions for the relevant load and trolley positions. Identify which dynamic and horizontal actions are included and the design basis used. A nominal 20 ton lifted load is not a complete runway design load, and it should not be divided evenly among wheels as a substitute for the selected reactions.

The responsible structural engineer should review the runway beams, rails, connections, columns and other supporting elements using the applicable load combinations and site condition. An existing crane runway does not establish compatibility with a replacement crane of the same nominal capacity.

COORDINATE BEFORE COMPARING OFFERS

Keep the clearance and runway schedules together

Provide the surveyed rail centres and levels, support drawings, working points, rigging details and operating cycle. Request a selected general arrangement, hook envelope and reaction schedule with matching revisions. Resolve any site modification and responsibility before installation planning.

Discuss your clearance and runway requirements

COMPARE A DEFINED HOIST-TYPE PACKAGE

State what the 20 ton offer includes

Identify the bridge, hoist trolley, drives, control arrangement, moving power feed and agreed safety functions. Use the Supply scope tab to allocate runway assessment, rails, erection, electrical work and acceptance. The archived LH-family description concerns intermittent service; sustained heavy production, special environments or unusual load cases require a separate suitability review. Confirm documentation, spare parts and warranty terms for the selected order.

Archived supplier reference

Historical supplier-listing information for context. Request a current quotation for your selected configuration and project scope.

Archived supplier-listing price rangeUS$6,000–7,000per set · MOQ 1 set

Range combines the price tiers shown in the saved listing. Captured 2026-10-12. This is not a current project quotation; capacity, dimensions, options, quantity, delivery and included services affect final price.

Show saved supplier price tiers
  • 1-9 setsUS$7,000 / set
  • ≥10 setsUS$6,000 / set

Archived supplier-listing reference. The saved price is not a current quotation; confirm configuration, quantity, shipping and included scope. View saved source listing ↗

04

One clear package for your buying team.

Bring engineering, purchasing and the installation team into the same scope before the purchase order.

Your layout is more useful than a generic catalogue.

Mark rail-top level, runway span, pickup/set-down positions, roof and service obstructions, rigging depth and load dimensions. Include support drawings and request the selected hook envelope and wheel-reaction schedule.

Send a drawing for review
YOU PROVIDE

Project brief

Load or working task, layout, operating cycle, destination and timing.

REVIEW TOGETHER

Technical offer

Selected configuration, interface drawing, component schedule and scope exceptions.

Compare like for like. Ask each bidder to identify the selected equipment, operating duty, interfaces and supply boundaries so differences in the offers are visible.
05

Questions before you request a quotation.

Why can building height differ from useful lifting height?

The available hook positions depend on the rail-top datum and the selected bridge, trolley, hoist and reeving outline. Below the hook, lifting attachments and the load also need space. Compare the complete envelope with the required workpoints and obstructions.

Does the 400/100t photograph show this 20 ton configuration?

No. It is a product-family reference photograph from the saved listing. Its visible rating and proportions do not establish the selected 20 ton equipment, lifting arrangement or support loads.

Can I divide 20 tonnes equally among the crane wheels?

No. Request the selected wheel reactions and design actions. These depend on the crane/trolley masses, wheel arrangement, load position and design basis. The responsible structural engineer must review the runway and supports using the applicable load combinations.

What should the 20 ton suspended-load requirement include?

20 t enquiry; include the lifted workpiece and below-hook slings, lifting beam and attachments in the suspended-load requirement. Do not deduct the integral hook block again; obtain crane/trolley self-weight separately for support design.

Is US$6,000–7,000 the current installed price?

The listing captured 2026-10-12 shows US$7,000 per set for one to nine sets and US$6,000 per set for at least ten. These are historical listing tiers, not a current selected or installed quotation. Compare the bridge/hoist package, runway work, power, delivery and site services on the same scope.

20 tonOverhead cranes
Request a quotation

Henan Mine Crane Group

Let’s plan your next lift.

Share your site and lifting requirements. Our team will review a suitable configuration.

Loading the inquiry form…